Article
Inside cement’s hottest control problem: taming kiln exhaust to dry the raw mill
Industry: Cement | Process: Raw_Milling_&_Blending
In dry-process cement, the cheapest dryer is the one you already have: the rotary kiln. Plants divert its hot exhaust from the preheater tower to the raw mill. This strips away water in clay- and shale-rich feeds that can be 10–20% wet. The physics are simple. Latent heat from waste gas does the drying. However, the control challenge is not simple. One wrong damper move and a mill can under-dry, plug, or send a baghouse past safe temperature.
Industry texts put preheater off‑gas usually at ~370–600°C. Designers routinely split this stream to the grinding circuit “before or during” milling, because “raw materials usually contain moisture and need to be dried.” The heat is usually supplied by waste gases from the rotary kiln or clinker cooler (www.atexdb.eu).
In practice, that means serious thermal power. One review describes a plant diverting ~60–70% of preheater exit gas through a crusher-dryer to the raw mill. That is enough to remove roughly 5–8% feed moisture (www.cementequipment.org). Boldyryev et al. modeled a case where 370°C exhaust heated 25°C raw to about 110°C, absorbing ~3.54 MW. In their balance, a 13.35 kW/K exhaust heat capacity raised 1.26×10^6 kg/h of raw by 85 K, yielding 3.537 MW (www.intechopen.com). The takeaway is that drying duty runs to the tens of MW. Therefore hot-gas control is central to both energy and quality.
Preheater exhaust as drying medium
A raw mill grinds limestone, clay and additives into “raw meal”. It works inside a tight temperature range to turn wet feed into powder that is ready for the kiln. Operators feed kiln and preheater gas in as “sweep air”. They increase it slowly because the mill is a large machine and its temperature changes slowly. The guidance says to keep the inlet gas at about 320°C and to start at about 95–120°C. Wait until the “after mill” and “after bag filter” temperatures settle near 85°C before loading fully (www.cementequipment.org, www.cementequipment.org).
Too cold and the “grinding plant would take away too much heat… product would not be dry,” risking high vibration and material spillage (www.cementequipment.org). Too hot and components face thermal stress; fast external heating can crack rollers and liners as the massive interiors lag (www.cementequipment.org).
Temperature bands and filter limits
The equipment downstream sets hard limits. Baghouse fabrics and cyclones are “rarely allowed above ~140°C”, so the gas must be cooled and controlled before it reaches the filter (www.intechopen.com). One plant cooled 370°C preheater gas to ~175°C in a wet gas cooler, then to ~105°C with ambient-air fans before the filter (www.intechopen.com).
With the controls tuned, operators aim for about 100–120°C at the mill inlet and hold the mill outlet and the filter at ~80–90°C. Data from Indonesia showed that with ~111 MW of heat input, the mill warmed the raw material from 25→110°C (www.intechopen.com). If all the gas bypasses the mill in this case, the fan cooling duty rises by ~19.4 MW. This shows how much the mill matters to the plant’s heat balance (www.intechopen.com).
Gas‑flow circuits and damper strategy
Plants design their gas paths to switch between modes. An Indian site changed from a 2-fan to a 3-fan circuit. This gives a “compound mode” where most preheater exhaust flows through the running raw mill and its ESP (electrostatic precipitator) fan before the baghouse. It also gives a “direct mode” (raw mill off) where all gas bypasses straight to the baghouse (www.thermaxglobal.com). Older systems have routed ~60–70% of exit gas through a hot-gas crusher-dryer feeding the mill (www.cementequipment.org).
Flow balance matters as much as temperature. If the mill gets too little gas, the feed stays wetter and grinding gets harder. Differential pressure rises as the mill over-fills. Too much heat risks over-drying, re-heating fines and stressing equipment. Therefore operators avoid >120°C at the inlet (www.intechopen.com). In the Boldyryev example, about 3.54 MW was needed just to heat raw from 25 to 110°C. Cut the flow and the outlet cools and wets out. Add too much and components drift hot (www.intechopen.com).
Start‑up ramps and steady PID control

Vertical roller mills (VRMs) integrate drying and grinding. Start-ups are staged. Increase inlet gas slowly until the mill outlet reaches ~85°C. Then hold for ~1 hour before full feed. Dampers and fans control the ramp (www.cementequipment.org).
Once stable, PLC loops (PID, proportional-integral-derivative) lock on inlet/outlet setpoints or on a ΔT band. Some plants measure feed moisture online and trim exchanger air accordingly. VRMs also manage the other extreme. If the feed gets too dry, water spray is needed to stabilize the grinding bed (www.cementindusneed.com). The control target is consistent: evaporate to roughly ≈0.5–1% raw mill outlet moisture while keeping components within design temperatures.
Operator KPIs and hourly checks
On the floor, the rhythm is disciplined. Teams log, typically hourly, the mill fan speed, damper position, inlet/outlet temperatures, and differential pressure—then adjust if deviations appear (www.cementequipment.org; www.cementequipment.org). Core KPIs include mill outlet moisture (target ≲1%) and inlet/outlet ΔT.
Energy and safety implications
Hot-gas drying saves fuel and raises throughput when it is done right. A survey of Chinese plants found raw milling used about 24% of total plant electricity, averaging 25.2 kWh/t of raw mix. As VRM and heat-recovery practices improved from 2014 to 2019, that fell from about 30.9 to 16.1 kWh/t (www.mdpi.com).
A case study at PT Semen Padang (Indonesia) measured the scale. A VRM raw mill processing ~1.26×10^6 kg/h needed ~4.01×10^8 kJ/h (≈112 MW) of heat input. The mill and dryer together ran at ~55% thermal efficiency. The study found the drying met the target moisture. (www.researchgate.net)
Poor balance drains power and brings hazards. Under-drying (too little hot gas) plugs mills and gives a “wetter” product. Over-drying (too much hot gas) raises fire and explosion risk and speeds up wear. Dust in a hot, dry mill can ignite. Hot fine raw can “cake” on rollers when the humidity swings. Standards set temperature ceilings in practice. Baghouse fabric must not go above about 140°C, so the circuit cannot send hotter gas downstream (www.intechopen.com). High inlet heat that is not checked can crack liners or even throw metal debris. Therefore the safeguards include alarms on mill shell temperature and dust deposition.
Bottom line for raw‑meal stability
Stable raw meal is uniform and dry, with moisture of about 1% or less. It begins with real-time control of kiln exhaust flow and temperature. Plants hold about 85°C at the mill outlet and quench hot gases before filtration. These plants report that they avoid thermal shocks to cyclones and filters (www.cementequipment.org; www.intechopen.com). When violations occur, corrective actions include diverting some gas away from the mill or temporarily injecting air. Over time, that discipline shows up as lower fuel use, because the plant does not overheat, and lower grinding power, because it does not “wet-grind.” The 16.1 kWh/t raw figure cited in the survey reflects this integrated drying efficiency. It captures both mill power and any hot-gas generation deficits (www.mdpi.com).
The control brief is precise but clear. Meter enough kiln/preheater gas to evaporate the load. Hold the mill and filters safely in the ~80–90°C band. Use PID-driven dampers and fans to keep it there. The Indonesian case stayed within design moisture limits. The Boldyryev balance sized heat at 3.54 MW for a modest temperature lift. Both underline the same point. In raw milling, hot-gas recirculation is a powerful ally only when it is tightly controlled (www.researchgate.net; www.intechopen.com).