In CCGT, a demin water failure means boiler pipe corrosion, turbine deposits, and unplanned outages. Reliability comes from three things: disciplined preventive maintenance, N+1 design, and spare parts inventory for the parts that matter most, plus a buffer of ≥24 hours.

Demin (demineralized) make-up water keeps a combined-cycle gas turbine (CCGT) plant running. When purity drops, the results are real: boiler pipe corrosion, turbine deposits and unplanned outages. The reliability target is simple but absolute: “quality water in the quantity you need every time”. That only happens when preventive care, spare parts and redundancy are built in from the design stage (www.mcilvainecompany.com) (www.waterworld.com).

Industry experts even emphasize an operational buffer: provide enough buffer storage, for example ≥24 hours of water inventory, so routine maintenance does not disrupt generation (www.mcilvainecompany.com). The point is that demin water availability must not become a constraint on electricity production.

Preventive Maintenance Program

Structured preventive maintenance (PM) cuts unplanned downtime by a lot. As WaterWorld summarizes: “just a few hours per month of preventative maintenance…can help reduce maintenance costs, improve plant performance, and extend the life of your equipment.” (www.waterworld.com). However, an unanticipated failure usually costs “tens of thousands of dollars” per event (www.waterworld.com).

A disciplined PM program includes periodic inspection, lubrication, calibration, and replacement of components before they fail. This prevents small defects from becoming major damage (www.waterworld.com). For example, monthly checks of pumps, valves, and instrumentation usually catch leaks or fouling before they force a shutdown. These checks include cleaning strainers, verifying degasser operation and testing conductivity gauges. Simple tasks also keep operation continuous and avoid expensive emergency repairs. Examples are cleaning a prefilter, for example a cartridge filter, or tightening connections.

Chemical dosing equipment also needs maintenance. Chemical pumps such as dosing pump must be calibrated and spare units prepared, so the reagent supply is not interrupted.

Data-Based Performance Monitoring

PM becomes more effective when a Performance Monitoring Program (PMP) supports it. The program records trends in conductivity, flow rate and pressure drop to detect early deviations (www.mcilvainecompany.com). Continuous analysis via sensors or periodic testing helps operators recognize resin exhaustion, membrane degradation or dosing errors long before failure (www.mcilvainecompany.com).

PMP does not need a large investment. It is essentially an inspection schedule and disciplined record-keeping (www.mcilvainecompany.com). Track resin bed run length, regeneration frequency, pump operating hours and reagent consumption. Then maintenance can be planned at the right intervals, when performance starts to decline, instead of waiting for a breakdown (www.mcilvainecompany.com) (www.waterworld.com). Good PM records also help you make O&M decisions on time, for example replacing membrane modules or important bearings before they fail. Resin monitoring, including ion exchange resin stock, is a key part of this strategy.

Quantitative Evidence for Maintenance

The impact can be measured. A reliability, availability and maintainability study at water treatment facilities showed that plant availability fell to about 92.7% when failures accumulated without a PM routine (www.researchgate.net). In practice, a demin plant reaches the target of >95% availability when PM is carried out correctly (www.waterworld.com).

  • Follow the OEM schedule for pumps, valves, blowers and dosing equipment. Replace worn seals, gaskets, bearings and impellers.
  • Service the resin and membranes regularly. Monitor resin exhaustion through slip or conductivity, then regenerate or replace on time. Some vendors recommend regeneration before breakthrough, based on throughput or time.
  • Calibrate instruments and check automation. Make sure level sensors, flow meters and conductivity probes are accurate, so anomalies are detected quickly.
  • Clean pretreatment filters and RO membranes while in service to prevent fouling. Monitor differential pressure as the backwash trigger. For chemical membrane cleaning, Industrial RO Membrane Cleaners is available.
  • Leak detection: repair immediately, including “weeping” valves. Addison/Weir notes that small leaks left to grow usually become the source of major outages (www.mcilvainecompany.com).

Reactive maintenance, the opposite approach, almost always leads to a higher TCO. A single emergency outage of just 8–24 hours can exceed the entire annual PM budget. Industry advisories usually repeat this costly lesson (www.waterworld.com).

N+1 Design Redundancy

Reliability by design is the second pillar. The global rule is N+1: if normal demand (N) needs X units, install X+1 so one unit can be offline without losing output. In practice, use several ion exchange trains or parallel membranes. Many large CCGTs have two to three complete demineralization trains, such as demineralizer, each at full capacity. Therefore one train can be regenerated or serviced while another train supplies the entire demand. This keeps 100% availability at full load.

Skipping redundancy is a common design trap. Addison/Weir highlights that “less‑than‑satisfactory design…means water production is limited by, or relies on, a single or unspared component”. That is a recipe for failure when that component has problems (www.mcilvainecompany.com). With multiple trains (or N+1), one upset does not force a shutdown. For example, if a cation exchanger channels or a pump fails, flow is immediately diverted to another train.

In membrane systems (RO/EDI), duplicating strings adds resilience. One string can be offline for cleaning without stopping the plant. Here, options such as RO brackish and EDI are usually installed in parallel or modularly. This fits modern membrane systems.

The N+1 approach also applies to supporting utilities such as the electrochlorination system for the marine growth prevention system (MGPS). With two parallel modules, one module can be cleaned or serviced while the other continues to carry the load. The electrochlorination module is available as the Betaqua Electrochlorination System. In demineralization terms, adding a low‑pressure blowdown skid or one extra mixed‑bed polisher cuts risk a lot without raising capex proportionally. For example, a mixed bed or a Condensate Polisher for Steam Power Plants.

Redundancy in Supporting Utilities

The N+1 principle also applies to ancillaries. Dual dosing pumps (one active, one standby) make sure the reagent supply does not stop because of a failure. Supporting equipment such as water-treatment ancillaries should ideally have a backup unit. An enlarged storage tank, with a 24-hour buffer as standard, gives time to repair equipment without service interruption (www.mcilvainecompany.com). A single level sensor or a single mechanical seal without backup is not acceptable in a high-reliability plant. Industry practice is to use dual sensors or a standby device.

Critical Spare Parts Inventory

Missing spares are a major cause of long outages (www.mcilvainecompany.com). Find the parts that would stop water production if they failed, and keep replacements: high-pressure pumps, vacuum pumps for degassing, instrumentation valves (2″–4″), conductivity probes, and transformer oil filtration carts. Even slow-moving items such as ion-exchange resin or RO membranes need to be kept as spares. Lead times can be weeks to months. A spare batch of resin lets you refill in an emergency without waiting for a shipment. Enough resin stock makes recovery faster.

A common policy is to hold at least one spare for each important component. That means one spare motor and rotor per pump type, vacuum pump belts, blowers, several impellers, and duplicate control cards. Failure history can guide material planning. If a valve or seal type lasts X hours, order so that the replacement is ready at the next PM interval.

International consultants say “critical spares must be identified” for every system “that must produce water…100% of the time it is needed” (www.mcilvainecompany.com). In practice, keep an inventory equal to several months of repair usage for key parts. For example, if a feed pump needs a seal kit every 6 months, stock at least two kits to cover one year. A CMMS (computerized maintenance management system) helps set reorder points so you avoid shortages or excess stock. Having spares also reduces the pressure to run equipment beyond its useful life. Without spares, a minor failure can force you to skip a regeneration schedule or run the resin bed until breakthrough. That risks damage downstream. Make sure every pump, valve, meter, or controller has a known spare along with its installation documents.

Measurable Outcomes and Trends

A demin plant focused on reliability shows clear improvements in availability and MTBF (mean time between failures). With strong PM and redundancy, availability >98–99% is usually reported. Without it, daily interruptions are not unusual. A study at a small water treatment facility showed availability falling from 97.96% to 92.67% when maintenance gaps let failures accumulate. That is a 5-point drop, equivalent to roughly one additional offline day per month (www.researchgate.net).

The cost of poor reliability can also be measured. Poor water quality reaching the boiler triggers turbine cleaning costs (thousands per event) or even forced derate. On the other side, every minute of downtime avoided adds generation revenue. Even conservatively, preventing two unscheduled one-hour outages per year can cover the entire annual spare‑parts budget. Surveys of industrial water users show that companies with a formal PM program usually report 30–50% lower maintenance costs and equipment downtime than reactive companies. One severe demin failure can trigger a generation outage costing “tens of thousands of dollars per hour” (www.waterworld.com). In short, “spending up‑front on PM, redundancy and spares is far cheaper than absorbing one large failure.”

Design and Operating Notes

All components need preventive care, duplication, or a clear backup. This covers pumps, resin, sensors and control systems. Industry guidance says three things are the foundation of performance: buffer storage (≥24 hours), multi‑train demin, including parallel architecture for membrane systems, and PM discipline. The guidance puts it as “quality water in the quantity you need every time” (www.mcilvainecompany.com) (www.waterworld.com). In practice, this policy keeps availability up and lifecycle costs down. It also keeps the plant consistent with generation obligations and environmental compliance.

Sources: technical and industry publications including Thermal Chemistry (Addison & Weir, “Water Management”) (www.mcilvainecompany.com) (www.mcilvainecompany.com), a hydro engineering journal (www.researchgate.net), WaterWorld expert articles (www.waterworld.com) (www.waterworld.com), and an integrated water treatment manual.